Data Centers May Pay for Grid Upgrades, Says Grid Operator

0

PJM proposes data centers cover grid upgrade costs, as regulators review new rules.

The image shows a series of electricity pylons and power lines against a clear sky, symbolizing the infrastructure of energy distribution.

2 min read

PJM Interconnection, a major grid operator covering much of the eastern U.S., has proposed a plan that could shift the cost of power line upgrades to data centers. The proposal, submitted to the Federal Energy Regulatory Commission (FERC), aims to allow states to bill large electricity users—including data centers—for the costs of transmission improvements they drive.

States Could Bill Data Centers for Grid Upgrades

PJM said the plan would give states transparent access to the costs of transmission improvements driven by data centers, as directed by FERC. This would empower states to bill large loads for those costs, according to the filing. Large Loads are defined as customers drawing 50 megawatts or more at one site.

“Under the proposal, the intent is that large loads/data centers bear the costs of the transmission upgrades they drive, not traditional customers,” said PJM spokesman Jeff Shields in a statement to the Daily Caller News Foundation.

Shields emphasized that PJM does not control how those costs are allocated, and the grid operator said it would make the costs and their drivers available on its website for public access. States would then use their power over retail rates to decide if certain customers should pay them.

Utilities that own the power lines would propose how to split and recover those costs, according to the filing. Data centers are projected to account for 30 of the 32 gigawatts of peak demand growth in PJM’s 2025 forecast, with the high-voltage grid serving over 67 million people in 13 states and the District of Columbia.

Data Centers Must Stay on Grid During Disturbances

PJM also submitted a separate proposal requiring data centers to stay on the grid during disturbances rather than switching to backup power. This follows a major event in July 2024 when nearly 3.9 gigawatts of data centers dropped off utility power and switched to their own generators, marking the largest such incident in PJM’s history.

“PJM operators were able to react so that no customers were in imminent danger of losing power,” Shields said.

PJM has asked FERC to rule on the ride-through proposal by January 15, 2027. If approved, the rules would take effect on January 16, 2027, for data centers and similar sites using 50 megawatts or more. Existing sites would have one year to comply.

Source: Daily Caller